I want to see with everyone's expertise on how I should set up this alignment off the Datums. There is Datum Target A1 and A2. and Datum B. How should I Tackle this? Attached is a layout of the Datums. Thank you for any help.
A1/A2 = Cylinder evaluations
B = Circle
A1-A2 = Line for axis (Level/Origin = 4 DOF)
B = Rotate about axis, origin along axis (=2DOF)
You now have all 6 DOF handled.
Beware, that the GDT reporting will not see all 6DOF controlled, it will only work for you in your alignment and legacy reporting.
A1/A2 = Cylinder evaluations
B = Circle
A1-A2 = Line for axis (Level/Origin = 4 DOF)
B = Rotate about axis, origin along axis (=2DOF)
You now have all 6 DOF handled.
Beware, that the GDT reporting will not see all 6DOF controlled, it will only work for you in your alignment and legacy reporting.
Thank you Very Much for your help R2. One other question. so I should level both Cylinders and then create a line and then Rotate Datum B and then Translate the 2 remaining Axis to Datum B?
When i manually measure Datum B and then measure the 2 outside cylinders, I created a plane (Mid Point) and did YPlus and leveled , I then rotate Datum B and then Translate the 2 remaining axis to Datum B, My Datum B is off in space. So i'm doing something incorrectly.