hexagon logo

SAP Scripting

Hey I need some non PC-DMIS Scripting help....

Do any of you guys have any experience with scripting in SAP?

What I'm trying to do is write a script that runs a report for me. I have it reporting the data and saving it but I cant figure out how to set the dates to the previous week. currently it is just running the report for the days I selected. I can post the code if that helps.
Parents
  • Update.... IT saw that I was scripting and blocked access to scripting for the entire plant. So there goes that haha.
  • That's what I'm saying. They didn't even notify me when it happened. I just found out once I was going to test my code. However... If they wont let me do it ill tell them to write me the code. I have already proven it to work. It normally takes about 3-4 hours a week to run these reports and format them in excel. I wrote a script to do it in 48 seconds. That includes saving the files under a new name and sending the data out in an email.

    That is a 99.64% time savings for the year. It wont be very hard to argue my side. 181 hours and 29 mins saved annually. or 22.6 work days. or 4.5 work weeks. I believe I will win this battle haha.
Reply
  • That's what I'm saying. They didn't even notify me when it happened. I just found out once I was going to test my code. However... If they wont let me do it ill tell them to write me the code. I have already proven it to work. It normally takes about 3-4 hours a week to run these reports and format them in excel. I wrote a script to do it in 48 seconds. That includes saving the files under a new name and sending the data out in an email.

    That is a 99.64% time savings for the year. It wont be very hard to argue my side. 181 hours and 29 mins saved annually. or 22.6 work days. or 4.5 work weeks. I believe I will win this battle haha.
Children
No Data