I checked one report found something suspicious, I think PLN2 should pass, but it was red and failed, but why? I am not good at Xact, anyone could explain to me? Thank you
Your Products have been synced, click here to refresh
Hello all.
I checked one report found something suspicious, I think PLN2 should pass, but it was red and failed, but why? I am not good at Xact, anyone could explain to me? Thank you
with a 1.3 upper tolerance, no way a 0.358 should show out of tolerance.
YOU NEED to show MIN/MAX on that dimension
Yes, that is my question. Why?
I checked the Report textual analysis with BOTH
Ok, I see. How to change the +Tol and -Tol to 0.65 to -0.65?
Ok, I see. How to change the +Tol and -Tol to 0.65 to -0.65?
It is one end profile. Based on the drawing and Xact chose