I have pc-dimis 2010. I write a program and run it through as i write it.My measurement checks will be correct but then as i go along writing the program and running through the new measurements I lose data from other measurements.My nominals will change and it will run through the program and then tell me that some of the features did not measure .What am I doing wrong? Any ideas?
Yes I am going to run the complete program when I am finished .This is the first program that has been written on this machine and I have been checking it step by step.The reason I posted in Portable is because we have a Discovery II that is on wheels out on the shop floor.
Yes I am going to run the complete program when I am finished .This is the first program that has been written on this machine and I have been checking it step by step.The reason I posted in Portable is because we have a Discovery II that is on wheels out on the shop floor.