I have a run chart layout that's already been run and the customer wants to change the tolerances. Is there any way I can do this in Datapage? Or do I have to go through pc dmis and change them point by point?
not for sure about the "new and improved" datapage, but with the old all you need to do is either:
1) Update the tolerances in the Pcdmis program and just send the current stats to update all the tolerances in the database
or
2) Go into the editor and edit each one by hand.
not for sure about the "new and improved" datapage, but with the old all you need to do is either:
1) Update the tolerances in the Pcdmis program and just send the current stats to update all the tolerances in the database
or
2) Go into the editor and edit each one by hand.